RFQ vs RFP vs RFI vs sources sought: which notice is a bid, and what to send
Short answer
Only two of these notices lead directly to an award. An RFQ (often posted as a combined synopsis/solicitation) asks for quotes under simplified procedures; an RFP asks for proposals in a negotiated buy. A sources sought notice and an RFI are market research: your reply is not an offer, but it can decide whether the job is set aside for small businesses. A presolicitation only announces what's coming.
Key facts
- Not offers — responses to RFIs "are not offers and cannot be accepted by the Government to form a binding contract." — FAR 15.201(e), checked Nov 10, 2026
- "A quotation is not an offer" — under an RFQ the government issues an order; a contract exists only when you accept it. — FAR 13.004(a), checked Nov 10, 2026
- At least 15 days — a presolicitation notice generally appears at least 15 days before the solicitation is issued. — FAR 5.203(a), checked Nov 10, 2026
- Over $25,000 — proposed contract actions are announced on SAM.gov. — FAR 5.101(a)(1), checked Nov 10, 2026
- 9th character — in a standard federal notice number,
Qmarks a request for quotations,Ra request for proposals,Ban invitation for bids. — FAR 4.1603(a)(3), checked Nov 10, 2026 - $350,000 — the simplified acquisition threshold; RFQs are the usual tool at or below it. — FAR 2.101; GSA, Pre-Award Notices, checked Nov 10, 2026
On this page ▾
Federal agencies post several kinds of notices on SAM.gov, and they look alike: a title, a number, a deadline, a contact. But they ask for very different things. Answer an RFI as if it were a bid, and you may give away pricing for nothing. Ignore a sources sought notice because "it's only a survey", and the job you wanted may never be set aside for small firms. This guide shows how to tell them apart in a minute.
Video: RFI, RFP and RFQ: Understanding the Difference
A free APEX counselor walks through the same four notice types and explains why answering an RFI can change who is allowed to bid later.Watch on YouTube ↗
- 3:07 — RFIs and sources sought notices are both market-research tools used while the agency plans the purchase.
- 3:37 — Agencies use RFI answers when they decide whether to set the work aside.
- 11:37 — If too few capable small businesses respond, the agency may decide not to restrict the competition to small firms.
- 14:34 — An RFP is a solicitation: it carries the work statement, clauses, proposal instructions and evaluation criteria.
- 15:47 — A quote sent for an RFQ does not by itself create a binding contract with the government.
Two questions to ask about any notice
Before you read the work statement, answer two questions. First: is the agency asking for a price it can award on? If the notice says it is "for information only" or "market research", the answer is no. Second: what exactly does it ask you to send, in what format, and by when? Every notice type has its own answer, and the table below sums them up.
Sources sought and RFI: market research, not a bid
A sources sought notice and a request for information (RFI) are both tools of market research under FAR Part 10. The agency is still deciding how to buy. FAR 10.002 lists one of the questions it must answer at this stage: whether its needs "can be met by small business concerns" that will likely submit competitive offers. Your reply is the evidence.
The difference is timing and focus. GSA describes an RFI as an early request "before defining a requirement", used to understand the market, price and delivery. A sources sought notice comes after the requirement is defined and is "primarily used to identify small businesses capable of performing" it. Neither creates a contract: responses "are not offers and cannot be accepted by the Government to form a binding contract" (FAR 15.201(e)).
Why bother answering? Because of the "rule of two": a purchase above the micro-purchase threshold and up to $350,000 is set aside for small business unless the contracting officer doesn't expect offers from two or more competitive small firms (FAR 19.502-2). If capable small businesses stay silent, GSA warns, "small businesses may lose a potential set-aside". How to write the reply itself is a separate topic — see our guide to responding to a sources sought notice (coming soon).
Presolicitation: a heads-up
A presolicitation notice tells you a solicitation is on its way. It usually gives the NAICS code, the planned set-aside and an expected release date. It is not a request for submittals. Its value is time: the notice generally has to appear at least 15 days before the solicitation is issued (FAR 5.203). Use those days to check that your SAM.gov registration is active and to line up subcontractors or equipment. Click "Follow" on SAM.gov so you get the solicitation and every amendment.
RFQ and combined synopsis/solicitation: a request for prices
A request for quotations (RFQ) is how agencies buy under simplified acquisition procedures (FAR Part 13), usually at or below the $350,000 simplified acquisition threshold. Many small commercial buys appear on SAM.gov as a combined synopsis/solicitation: FAR 12.603 lets the agency merge the announcement and the solicitation "into a single document", which saves time for both sides. That's why the notice description itself may contain the instructions and the deadline.
One legal detail matters: "A quotation is not an offer" (FAR 13.004). The government answers your quote with an order, and the contract is formed when you accept that order. In practice this means you can still decline if the order terms differ from your quote — but don't count on a contract just because you sent a price.
RFP: a negotiated buy
A request for proposals (RFP) is used "in negotiated acquisitions to communicate Government requirements to prospective contractors and to solicit proposals" (FAR 15.203). Expect a longer document with a performance work statement, proposal instructions and evaluation criteria, and often a technical volume, past performance and price evaluated separately. RFPs are heavier to answer. For a first bid, many small firms start with RFQs and come back to RFPs once they have a track record.
The five types side by side
Five notice types side by side
| Notice type | What it is | FAR part | Is your reply an offer? | What to send | If you stay silent |
|---|---|---|---|---|---|
| Sources Sought | Survey of capable firms for a defined need | Part 10 (market research) | No | Exactly what it asks: company data, size and status, relevant experience, answers to its questions | The agency may not see two capable small firms and skip the set-aside |
| RFI (Request for Information) | Early survey of the market, price, delivery | Part 10; 15.201(e) | No | Information and ideas it asks for; a price range only if requested | You lose a chance to shape the requirement |
| Presolicitation | Advance notice of a coming solicitation | Part 5 (5.203) | Nothing to send | Nothing; follow the notice and get ready | You may see the solicitation late |
| RFQ / Combined Synopsis/Solicitation | Request for prices under simplified procedures | Part 13 (and 12.603 for combined) | No — a quote isn't an offer; the order is | A complete quote in the format, to the address and by the time stated | No award |
| RFP (Request for Proposals) | Formal solicitation in a negotiated buy | Part 15 | Yes — a proposal is an offer | Proposal volumes exactly as section L or the instructions require | No award |
Sources Sought
- What it is
- Survey of capable firms for a defined need
- FAR part
- Part 10 (market research)
- Is your reply an offer?
- No
- What to send
- Exactly what it asks: company data, size and status, relevant experience, answers to its questions
- If you stay silent
- The agency may not see two capable small firms and skip the set-aside
RFI (Request for Information)
- What it is
- Early survey of the market, price, delivery
- FAR part
- Part 10; 15.201(e)
- Is your reply an offer?
- No
- What to send
- Information and ideas it asks for; a price range only if requested
- If you stay silent
- You lose a chance to shape the requirement
Presolicitation
- What it is
- Advance notice of a coming solicitation
- FAR part
- Part 5 (5.203)
- Is your reply an offer?
- Nothing to send
- What to send
- Nothing; follow the notice and get ready
- If you stay silent
- You may see the solicitation late
RFQ / Combined Synopsis/Solicitation
- What it is
- Request for prices under simplified procedures
- FAR part
- Part 13 (and 12.603 for combined)
- Is your reply an offer?
- No — a quote isn't an offer; the order is
- What to send
- A complete quote in the format, to the address and by the time stated
- If you stay silent
- No award
RFP (Request for Proposals)
- What it is
- Formal solicitation in a negotiated buy
- FAR part
- Part 15
- Is your reply an offer?
- Yes — a proposal is an offer
- What to send
- Proposal volumes exactly as section L or the instructions require
- If you stay silent
- No award
Read the notice number: the 9th character
Here's a shortcut most guides skip. A standard federal procurement number has 13 to 17 characters, and position 9 shows the type of instrument (FAR 4.1603): Q — request for quotations, R — request for proposals, B — invitation for bids. In 15F06727Q0000010 (an open FBI window-cleaning RFQ in Clarksburg, WV) the 9th character is Q. In the open civilian cleaning notices we counted on Nov 10, 2026, 22 of 23 had a Q in that position. The exception was a Coast Guard notice with a free-form number — so treat the letter as a hint, and confirm with the notice type and the text.
Traps that cost first-timers
- Pricing an RFI in detail. An RFI rarely needs a full price. If it asks for a rough order of magnitude, give a range and say what it depends on.
- Skipping a sources sought notice. It's the cheapest way to tell a buyer you exist, and it feeds the set-aside decision.
- Missing the solicitation after the presolicitation. The number stays the same; the type changes. Follow the notice on SAM.gov.
- Reading only the summary of a combined synopsis/solicitation. The instructions are often in attachments and amendments.
- Assuming the RFQ is a contract. It isn't until you accept the order.
Real notice
Semi-annual window cleaning, San Diego VA Health Care System — Department of Veterans Affairs
One number, 36C26227Q0081, went through three notice types in nine days:
| Date | Type on SAM.gov | What it said | Original |
|---|---|---|---|
| Oct 29, 2026 | Sources Sought | "It is neither a solicitation announcement nor a request for proposals or quotes." Replies due Nov 5, 10:00 a.m. (UTC−7). Planned set-aside: SDVOSB. | SAM.gov ↗ |
| Nov 4, 2026 | Presolicitation | Heads-up that the solicitation is coming | SAM.gov ↗ |
| Nov 6, 2026 | Solicitation (RFQ — Q in position 9) | Window cleaning twice a year; quotes due Dec 7, 2026, 1:00 p.m. (UTC−7). Amendment 0001 on Nov 13 answered vendor questions and set a site visit for Nov 19 | SAM.gov ↗ |
Oct 29, 2026
- Type on SAM.gov
- Sources Sought
- What it said
- "It is neither a solicitation announcement nor a request for proposals or quotes." Replies due Nov 5, 10:00 a.m. (UTC−7). Planned set-aside: SDVOSB.
- Original
- SAM.gov ↗
Nov 4, 2026
- Type on SAM.gov
- Presolicitation
- What it said
- Heads-up that the solicitation is coming
- Original
- SAM.gov ↗
Nov 6, 2026
- Type on SAM.gov
- Solicitation (RFQ —
Qin position 9) - What it said
- Window cleaning twice a year; quotes due Dec 7, 2026, 1:00 p.m. (UTC−7). Amendment 0001 on Nov 13 answered vendor questions and set a site visit for Nov 19
- Original
- SAM.gov ↗
FirstContract analysis: the sources sought notice asked for company name, contacts, CAGE code, tax ID, small-business type and a capability statement — and said that if service-disabled veteran-owned firms didn't respond in sufficient numbers, "an alternate set-aside or full and open competition may be determined". That's the rule of two in action. Two lessons for a first-timer. First, the survey asked for a "DUNS number", which SAM.gov no longer uses: today it's the Unique Entity ID (SBA). Agency templates lag behind; answer with what exists now. Second, the set-aside field on the solicitation keeps changing on SAM.gov: empty at first, marked SDVOSB on Nov 12, 2026, and empty again in the Nov 13 amendment — so confirm the set-aside in the solicitation document itself before you spend time on a quote.
FAQ
Is a sources sought notice the same as an RFI?
Close, but not the same. Both are market research. An RFI usually comes earlier and asks for ideas; a sources sought notice comes after the need is defined and looks for capable small businesses.
Do I have to answer a sources sought notice to bid later?
Usually no rule requires it. But your answer can affect whether the job is set aside for small firms. Read the notice: a few say otherwise.
What's an IFB?
An invitation for bids under sealed bidding (FAR Part 14), marked B in position 9 of the number. It's less common for small service buys.
Can FirstContract answer notices for me?
No. You write and submit your own replies. FirstContract helps you read notices and list what each one asks for.
FirstContract
Your next step
- Open one notice in your NAICS code on SAM.gov and name its type before you read anything else.
- Click "Follow" on any sources sought or presolicitation that fits, so you see the solicitation and amendments.
- Ask your local APEX Accelerator to review your first reply — the service is free.
- Get the requirement checklist for your first bid — join the FirstContract pilot.
The pilot isn't open yet. Send one short email and we'll write to you when spots open. Joining doesn't reserve a spot.
Starter $59, Builder $149, Team $299 a month. We don't submit bids or guarantee awards. Not a government agency. Not legal advice.
Sources and method
- FAR 15.201 — acquisition.gov. checked Nov 10, 2026
- FAR 13.004 — acquisition.gov. checked Nov 10, 2026
- FAR 15.203 — acquisition.gov. checked Nov 10, 2026
- FAR 5.203 — acquisition.gov. checked Nov 10, 2026
- FAR 5.101 — acquisition.gov. checked Nov 10, 2026
- FAR 4.1603 — acquisition.gov. checked Nov 10, 2026
- FAR 10.002 — acquisition.gov. checked Nov 10, 2026
- FAR 12.603 — acquisition.gov. checked Nov 10, 2026
- FAR 19.502-2 — acquisition.gov. checked Nov 10, 2026
- FAR 2.101 — acquisition.gov. checked Nov 10, 2026
- How to Respond to Pre-Award Notices — GSA OSDBU. checked Nov 10, 2026
- Basic requirements — SBA. checked Nov 10, 2026
- Notice 36C26227Q0081 (3 versions) (links in the example above) — VA, SAM.gov; public Contract Opportunities data file, Nov 10, 2026, 04:30 GMT. checked Nov 13, 2026
- Count “22 of 23” — Our count from the same data file. checked Nov 10, 2026
- RFI, RFP and RFQ: Understanding the Difference — Maryland APEX Accelerator, YouTube. checked Nov 10, 2026
How we made this: drafted with AI by FirstContract, then checked by a second AI review against the official sources below on Nov 10, 2026. No human legal review. This is not legal advice.
What changed: Nov 11, 2026 — first version.